Road Improvement Schemes in Charnwood Borough

Each scheme entry contains the location of the scheme and a description of what is being done there. "Scheme Status" describes the sequence of each scheme's development:-
  1. Design Underway
  2. Consultation Underway
  3. Awaiting Construction
  4. Construction Underway
  5. Complete
Schemes marked as "Reserve"  may be designed and consulted on this year but may not be constructed until later.
Cost Band - This column indicates the estimated cost of the scheme.
"A" = £200,000+
"B" = £50,000 - £200,000
"C" = Under £50,000
Anticipated Construction - This column indicates the period in the current financial year when the scheme is expected to be completed.
"Q1" = April to June.
"Q2" = July to September.
"Q3" = October to December
"Q4" = January to March
Some schemes have links to their own pages which contain more detailed information.
To see all road improvements schemes in Leicestershire planned for this financial year please click here to see our Road Improvement Schemes page.
For information on larger road schemes please use this link to Major Transport Projects.
Disclaimer -
This information is not definitive and we cannot guarantee it is a complete and up to date list of all County Council schemes.  It should not be used for the purposes of compiling a property search, for accurate and up to date information for this purpose please go to the Land Charges and Searches section.
Not one of our schemes?  Call the Customer Service Centre for further assistance on 0116 305 0001.
Parish Location Details Status Cost Band Anticipated Construction
Anstey Link Road Traffic calming Developer Funded - Consultation Underway B Q4
Barrow Upon Soar Cotes Road/Nottingham Road Traffic calming Developer Funded - Awaiting Construction B Q4
Loughborough Loughborough, Belton Road West Extension Footway/Cycle track Complete B Q2
Loughborough Fairmeadows Way - Woodbrooke Vale Primary School Traffic calming & waymarkers Complete C Q3
Loughborough Forest Road Footway/Cycle track & Toucan crossing Awaiting Construction B Q4
Loughborough Forest Road/Nanpantan Road Footway Improvements/Cycle facilities On Hold - -
Loughborough Maxwell Drive - Stonebow Primary School Waymarkers & cycle signing Design underway C Q4
Loughborough Shelthorpe Primary School Advisory 20mph School safety zone Complete C Q2
Loughborough Woodthorpe Roundabout Road safety improvements Consultation Underway C Q4
Loughborough/Quorn A6 between cemetery and A6004 roundabout New Safety Camera Awaiting construction C Q4
Shepshed Iveshead Road/Charley Road Surfacing, horizontal/vertical re-alignment Consultation underway B Q4
Syston Melton Road - Roundhill Community College Advisory 20mph School safety zone Awaiting Construction C Q4
Syston Melton Road - Roundhill Community College Footway/Cycle tracks - Phase 1 and 2 Awaiting Construction B Q4
Syston St Peter & St Paul C of E Primary School Advisory 20mph School safety zone Externally funded - Complete C Q3
Syston Wreake Valley College Advisory 20mph School safety zone Externally funded - complete C Q3
Syston Wreake Valley Link Cycle Links Externally funded - Construction underway C Q3/Q4
Thurmaston A607 Newark Road/Melton Road Roundabout Signal visibility changes Awaiting construction C Q4
Thurmaston A607 Newark Road, Humberstone Lane to Barkby Thorpe Lane Footway/Cycle Track Externally funded (part) - Complete B Q3Q4
Wanlip Rectory Road Traffic calming Developer Funded -Complete C Q3
Various A607 from A46 to Melton Route signing and surface improvements Awaiting construction B Q4
Various A6, Loughborough to M1 junction 24 Route improvements including speed limits, gap closures & signs. Awaiting construction B Q4
Various A6, Loughborough to Birstall Route signing and surface improvements Reserve - Design underway B 2012/13
Various Loughborough South West & the Wolds Villages Community Forum funded cycle parking Complete C Q1
Various Loughborough Various Congestion management programme Reserve - Design underway A 2012/13
Various Loughborough Various Cycle network signing (completion) Construction underway C 2011/12
Various Rural Bus Partnership - Countywide Grant support to local communities for bus shelters Design underway C 2011/12
Various Soar Valley Cycle signing Externally funded - Complete B Q3
Various Connect2 Watermead Park Footway/Cycle track Construction underway C 2011/12
Various Various schools - Countywide Cycle parking in partnership with Sustrans Construction underway A Q2/Q3/Q4
Various Various - Countywide Footway improvements Design underway C 2011/12
Various Various - Countywide Rights of way network improvements Design underway B 2011/12

Page Last Updated: 24 January 2012