Key Information - normally required at the Preliminary Design Stage
|
|
General
|
|
- Details of planning consent and conditions
|
|
- Current state of S278/S38 agreement where appropriate
|
|
- Details of any residential properties likely to result in Part 1 claims or noise insulation as part of Land Compensation Act
|
|
- Stage 1 safety audit with designers response
|
|
- Details of pedestrians/cyclist/public transport provision
|
|
- Intended treatment of existing Rights of Way
|
|
- Traffic flows or traffic study reports
|
|
- Evidence of public participation or meetings with relevant third parties
|
|
- If not already submitted provide information normally required at the feasibility stage
|
|
Layout
|
|
- Any known relaxations departures from design standards to be identified in the design
|
|
- Design speed selection for each highway link
|
|
- Justification of highway cross section (carriageway width etc) for appropriate traffic flows where not already agreed or approved (by us or the planning authority).
|
|
- Justification of junction type where not already agreed or approved (by us or the planning authority). Agree any traffic signal geometric requirements
|
|
- 1:1250/1:500 horizontal plans of existing and proposed layout
|
|
- Provisional highway boundary position ensuring that signage, street lighting, maintenance are provided for
|
|
- Areas intended for landscaping and provisional proposals
|
|
- Provisional longitudinal sections of centreline with k values
|
|
- New cross sections or typical cross sections showing relationship of proposed profiles with existing ground level
|
|
- Visibility splays
|
|
- Consideration for requirements for safety fence
|
|
Drainage
|
|
- Drainage strategy showing intended outfalls
|
|
- Environment Agency approval for discharge of drainage
|
|
- Easement if present or proposed
|
|
- Proposals for pumps or throttles and temporary storage areas
|
|
- Drainage longitudinal sections and indication of those pipes to be adopted by LCC
|
|
Earthworks
|
|
- Details of borrow pits and or temporary storage areas
|
|
- Sources of imported material
|
|
- Recycling or other environmental strategy
|
|
- Ground investigation reports and identification of any special features or geotechnical aspects
|
|
Signing
|
|
- Direction signing strategy
|
|
Structures
|
|
- Structures. General arrangement of structures and AIP Document in accordance with BD 2/02
|
|
Statutory undertakers (for example, gas, water, cable TV)
|
|
- If it is appropriate at this stage to serve a provisional NRSWA Notice, provide 25 plans suitable for this purpose
|
|
Environmental aspects and heritage
|
|
- Identification
|
|
- Permit to work and licenses
|
|
- Reports and findings of surveys and searches
|